Table of Contents

Search

  1. Preface
  2. Analyst Service
  3. Catalog Service
  4. Content Management Service
  5. Data Integration Service
  6. Data Integration Service Architecture
  7. Data Integration Service Management
  8. Data Integration Service Grid
  9. Data Integration Service REST API
  10. Data Integration Service Applications
  11. Enterprise Data Preparation Service
  12. Interactive Data Preparation Service
  13. Informatica Cluster Service
  14. Mass Ingestion Service
  15. Metadata Access Service
  16. Metadata Manager Service
  17. Model Repository Service
  18. PowerCenter Integration Service
  19. PowerCenter Integration Service Architecture
  20. High Availability for the PowerCenter Integration Service
  21. PowerCenter Repository Service
  22. PowerCenter Repository Management
  23. PowerExchange Listener Service
  24. PowerExchange Logger Service
  25. SAP BW Service
  26. Search Service
  27. System Services
  28. Test Data Manager Service
  29. Test Data Warehouse Service
  30. Web Services Hub
  31. Application Service Upgrade
  32. Appendix A: Application Service Databases
  33. Appendix B: Connecting to Databases from Windows
  34. Appendix C: Connecting to Databases from UNIX or Linux
  35. Appendix D: Updating the DynamicSections Parameter of a DB2 Database

Application Service Guide

Application Service Guide

Running on a Grid

Running on a Grid

When a service is running on a grid, the failover behavior depends on the following sources of failure:
Master Service Process
If you disable the master service process, the Service Manager elects another node to run the master service process. If the master service process shuts down unexpectedly, the Service Manager tries to restart the process before electing another node to run the master service process.
The master service process then reconfigures the grid to run on one less node. The PowerCenter Integration Service restores the state of operation, and the workflow fails over to the newly elected master service process.
The PowerCenter Integration Service can recover the workflow based on the workflow state and recovery strategy. If the workflow was enabled for high availability recovery, the PowerCenter Integration Service restores the state of operation for the workflow and recovers the workflow from the point of interruption. When the PowerCenter Integration Service restores the state of operation for the service, it restores workflow schedules, service requests, and workflows. The PowerCenter Integration Service performs failover and recovers the schedules, requests, and workflows.
If a scheduled workflow is not enabled for high availability recovery, the PowerCenter Integration Service removes the workflow from the schedule.
Worker Service Process
If you disable a worker service process, the master service process reconfigures the grid to run on one less node. If the worker service process shuts down unexpectedly, the Service Manager tries to restart the process before the master service process reconfigures the grid.
After the master service process reconfigures the grid, it can recover tasks based on task state and recovery strategy.
Because workflows do not run on the worker service process, workflow failover is not applicable.
Service
When the PowerCenter Integration Service becomes unavailable, you must enable the service and start the service processes. You can manually recover workflows and sessions based on the state and the configured recovery strategy. Workflows start if they are configured to run continuously or on initialization. You must reschedule all other workflows.
Node
When the node running the master service process becomes unavailable, the failover behavior is the same as the failover for the master service process. When the node running the worker service process becomes unavailable, the failover behavior is the same as the failover for the worker service process.
You cannot configure a PowerCenter Integration Service to fail over in safe mode when it runs on a grid.