Table of Contents

Search

  1. Preface
  2. Installation Overview
  3. Pre-Installation Tasks
  4. Hub Store Installation
  5. Hub Server Installation
  6. Hub Server Post-Installation Tasks
  7. Process Server Installation
  8. Process Server Post-Installation Tasks
  9. ActiveVOS Post-Installation Tasks for the Application Server
  10. ActiveVOS Post-Installation Tasks for the Business Entity Adapter
  11. Resource Kit Installation
  12. Resource Kit Post-Installation Tasks
  13. Troubleshooting the MDM Hub
  14. Uninstallation

Installation Guide for IBM Db2 with Red Hat JBoss

Installation Guide for IBM Db2 with Red Hat JBoss

Manually Deploying the Process Server Application (Conditional)

Manually Deploying the Process Server Application (Conditional)

You can manually deploy the
Process Server
application. You must deploy the Process Server application from the Process Server installation directory.
If the installation is in an application server multi-node or a cluster environment, first deploy the Process Server application on one node, and then deploy the Process Server application on the other nodes. Ensure that you deploy the Process Server application on the same machine on which you installed the Process Server.
  1. Stop the JBoss application server.
  2. If you have an existing deployment, delete the
    siperian-mrm-cleanse.ear
    deployment file from the following JBoss deployment directory:
    <
    JBoss installation directory
    >\standalone\deployments
  3. Copy the
    siperian-mrm-cleanse.ear
    deployment file from the
    Process Server
    installation directory to the JBoss deployment directory.
  4. Start the JBoss application server.
For more information about deploying applications, see the JBoss documentation.