Table of Contents

Search

  1. Preface
  2. Summary of PowerExchange New Features and Changes
  3. PowerExchange Installation and Upgrade
  4. PowerExchange Agent
  5. PowerExchange Client for PowerCenter
  6. PowerExchange Condense
  7. PowerExchange Listener
  8. PowerExchange Logger for Linux, UNIX, and Windows
  9. PowerExchange Navigator
  10. PowerExchange Monitoring and Tuning
  11. PowerExchange Utilities
  12. PowerExchange for Adabas
  13. PowerExchange for CA Datacom
  14. PowerExchange for DB2 for i
  15. PowerExchange for DB2 for Linux, UNIX, and Windows
  16. PowerExchange for DB2 for z/OS
  17. PowerExchange for CA IDMS
  18. PowerExchange for IMS
  19. PowerExchange for Microsoft SQL Server
  20. PowerExchange for MySQL
  21. PowerExchange for Oracle
  22. PowerExchange for PostgreSQL
  23. PowerExchange for SAP HANA
  24. PowerExchange for VSAM and Flat Files
  25. PowerExchange ODBC

Ability to Skip Data Rows for IMS Unload Data Sets During a Row Test

Ability to Skip Data Rows for IMS Unload Data Sets During a Row Test

You can now specify the number of initial rows of data to skip when performing a row test that fetches data for IMS unload data sets.
Use the following field in the
Database Row Test
dialog box:
Skip First
n
Rows
New for IMSUNLD
. Indicates the number of initial rows of data to skip when the row test fetches data for display. If you are performing a row test on a large file, you can use this option to have the row test skip to a specific point in the file before displaying data. This option can help you diagnose problems in large files faster because only the data of potential interest is returned for analysis.
For this existing option to be available for IMS unload files, select
IMSUNLD
in the
DB Type
list when you configure the row test.
Valid values are 0 to 99999. Default is 0, which causes no rows to be skipped.
For more information, see the "Database Row Test Dialog Box" chapter in the
PowerExchange Navigator User Guide
.

0 COMMENTS

We’d like to hear from you!