Supplier Profile Change Approval Process

Supplier Profile Change Approval Process

The default change approval process is a four-step process. The process begins when a business manager creates or edits a supplier profile.
The following diagram shows an overview of the process and highlights the people activities.
The process includes four evaluation activities: commodity, credit, contract, and risk.
The first people activity is the commodity evaluation, which requires a commodity manager to review the update. If the commodity manager accepts it, the update moves on to a credit evaluation and then a contract evaluation. The last approval step is a risk evaluation. If the compliance manager believes the risk is acceptable, the manager approves the update and notifies the supplier. At any stage, a manager can reject the update.
The following table summarizes the people activities within the process, the required role, and the possible actions:
People Activity
Role Assigned
Possible Actions
Commodity Evaluation
CommodityManager
  • Accepts the update. This action sends the update onto the Credit Evaluation step.
  • Rejects the update. This action deletes the pending record containing the changes.
  • Disclaims the task with an explanation so that someone else can claim it.
Credit Evaluation
FinanceManager
  • Accepts the update. This action sends the update onto the Contract Evaluation step.
  • Rejects the update with explanation. This action sends the update back to the Commodity Evaluation step.
  • Disclaims the task with an explanation so that someone else can claim it.
Contract Evaluation
ContractManager
  • Accepts the update. This action sends the update onto the Risk Evaluation step.
  • Rejects the update with explanation. This action sends the update back to the Commodity Evaluation step.
  • Disclaims the task with an explanation so that someone else can claim it.
Risk Evaluation
ComplianceManager
  • Approves the update. This action applies the changes to the master data.
  • Rejects the update with explanation. This action sends the update back to the Commodity Evaluation step.
  • Disclaims the task with an explanation so that someone else can claim it.