Import the Operational Data Store Event Loader Workflow to PowerCenter
Import the Operational Data Store Event Loader Workflow to PowerCenter
Import the operational data store (ODS) event loader workflow to load event information from the
B2B Data Exchange
repository to the
B2B Data Exchange
ODS.
If you use an existing workflow with the name DX_ETL, rename the existing workflow in PowerCenter Repository Manager before you import the ODS event loader workflow, or import the workflow to a different folder.
After you import the ODS event loader workflow, do not run the workflow manually. The workflow must start at the scheduled time. If you start the workflow manually it might fail to store aggregated events in the
B2B Data Exchange
ODS.
In the PowerCenter Workflow Manager, select
Connections
Relational
.
Add the
DX_REPO
connection for the
B2B Data Exchange
repository.
Add the
DX_ODS
connection for the
B2B Data Exchange
ODS.
In the PowerCenter Repository Manager, import the
B2B Data Exchange
ODS workflow file. The name of the workflow file depends on type of database on which the ODS is installed.
In the PowerCenter Workflow Manager, connect to the PowerCenter repository.
If
B2B Data Exchange
was previously installed at your site, and you want to exclude old events from the dashboard reports, instruct the workflow to load only events that finished processing after a specific date and time. Click
Workflow
Edit
Variables
and change the value of the
$$WF_Last_Load_End_Time
variable.
Do not change the variable after the first time the workflow runs.
By default, the workflow runs every 15 minutes. You can schedule the workflow start time.
Right-click the PowerCenter Integration Service that you want to assign to the ODS event loader workflow and select
Assign to Workflows
.
The
Assign Integration Service
dialog box appears.
Select the
DX_ETL
check box and then click
Assign
.
PowerCenter assigns the Data Integration Service to the ODS event loader workflow.