Table of Contents

Search

  1. Preface
  2. Installation Overview
  3. Before You Begin
  4. Pre-Installation Tasks
  5. Data Integration Hub Installation
  6. Post-Installation Tasks
  7. Upgrading Data Integration Hub
  8. Starting and Stopping Data Integration Hub
  9. Optional Data Integration Hub Configuration
  10. Installing and Configuring the Data Integration Hub Accelerator for Data Archive
  11. Troubleshooting the Data Integration Hub Installation
  12. Uninstallation

Installation and Configuration Guide

Installation and Configuration Guide

Import the Operational Data Store Event Loader Workflow to PowerCenter

Import the Operational Data Store Event Loader Workflow to PowerCenter

This section applies only if you use the Dashboard using operational data store.
Import the operational data store (ODS) event loader workflow to load event information from the
Data Integration Hub
repository to the
Data Integration Hub
ODS.
If you use an existing workflow with the name DX_ETL, rename the existing workflow in PowerCenter Repository Manager before you import the ODS event loader workflow, or import the workflow to a different folder.
After you import the ODS event loader workflow, do not run the workflow manually. The workflow must start at the scheduled time. If you start the workflow manually it might fail to store aggregated events in the
Data Integration Hub
ODS.
  1. In the PowerCenter Workflow Manager, select
    Connections
    Relational
    .
  2. Add the
    DX_REPO
    connection for the
    Data Integration Hub
    repository.
  3. Add the
    DX_ODS
    connection for the
    Data Integration Hub
    ODS.
  4. In the PowerCenter Repository Manager, import the
    Data Integration Hub
    ODS workflow file. The name of the workflow file depends on type of database on which the ODS is installed.
    Database Type
    Workflow Location and Name
    Oracle
    <
    DIH
    InstallationDir>\powercenter\ETL\DX_ETL.xml
    Microsoft SQL Server
    <
    DIH
    InstallationDir>\powercenter\ETL\DX_ETL_SQLSERVER.xml
  5. In the PowerCenter Workflow Manager, connect to the PowerCenter repository.
  6. If
    Data Integration Hub
    was previously installed at your site, and you want to exclude old events from the dashboard reports, instruct the workflow to load only events that finished processing after a specific date and time. Click
    Workflow
    Edit
    Variables
    and change the value of the
    $$WF_Last_Load_End_Time
    variable.
    Do not change the variable after the first time the workflow runs.
  7. By default, the workflow runs every 15 minutes. You can schedule the workflow start time.
  8. Right-click the PowerCenter Integration Service that you want to assign to the ODS event loader workflow and select
    Assign to Workflows
    .
    The
    Assign Integration Service
    dialog box appears.
  9. Select the
    DX_ETL
    check box and then click
    Assign
    .
    PowerCenter assigns the Data Integration Service to the ODS event loader workflow.