Installation and Upgrade Guide

Installation and Upgrade Guide

Step 10. Submit CDC Jobs

Step 10. Submit CDC Jobs

To allocate the data sets required for CDC operations, submit the CDC jobs in the upgrade RUNLIB library based on the upgrade option that you selected.
  1. Submit the SETUCC1E or SETUCC1N job to allocate the required data sets.
    • If you selected the
      Upgrade by Using Existing Data Set Names
      option, submit SETUCC1E.
    • If you selected the
      Upgrade by Using New Data Set Names
      option, submit SETUCC1N.
  2. Submit the additional CDC jobs that are listed in the following table:
    Upgrade Option
    Jobs
    Description
    Upgrade by Using Existing Data Set Names
    BKUPDSUE, followed by INSPWXUE
    Do not submit INSPWXUE until BKUPDSUE finishes successfully.
    The BKUPDSUE job makes backup copies of the data sets that you selected on the
    Backup Data Sets
    page.
    The INSPWXUE job populates existing software libraries with new members.
    Upgrade by Using New Data Set Names
    XIZZZ998, optionally followed by XIZZZ999
    The XIZZZ998 job deletes temporary members from the RUNLIB library and builds JCL.
    The optional XIZZZ999 job deletes members from the RUNLIB library after the JCL is copied to the final destination libraries.