When converting an existing Task, you can choose a different version.
Open the Project in which to change the Task version Number.
From the page toolbar, click
Show XML
.
In the Project XML page, locate the version number for a Task and change it to the desired version. In the example below, the yellow highlight indicates where the Read Excel Task could be updated to 2.0 or where the Read Excel Task could be downgraded to 1.0.
When complete, click the
Validate and Save
button. The changes will be visible in the Project Designer.