Table of Contents

Search

  1. Preface
  2. Welcome to Informatica Process Developer
  3. Using Guide Developer for the First Time
  4. Getting Started with Informatica Process Developer
  5. About Interfaces Service References and Local WSDL
  6. Planning Your BPEL Process
  7. Participants
  8. Implementing a BPMN Task or Event in BPEL
  9. Implementing a BPMN Gateway or Control Flow
  10. Using Variables
  11. Attachments
  12. Using Links
  13. Data Manipulation
  14. Compensation
  15. Correlation
  16. What is Correlation
  17. What is a Correlation Set
  18. Creating Message Properties and Property Aliases
  19. Adding a Correlation Set
  20. Deleting a Correlation Set
  21. Adding Correlations to an Activity
  22. Rules for Declaring and Using Correlation Sets
  23. Correlation Sets and Engine-Managed Correlation
  24. Event Handling
  25. Fault Handling
  26. Simulating and Debugging
  27. Deploying Your Processes
  28. BPEL Unit Testing
  29. Creating POJO and XQuery Custom Functions
  30. Custom Service Interactions
  31. Process Exception Management
  32. Creating Reports for Process Server and Central
  33. Business Event Processing
  34. Process Central Forms and Configuration
  35. Building a Process with a System Service
  36. Human Tasks
  37. BPEL Faults and Reports

Designer

Designer

Adding a Link with no Transition

Adding a Link with no Transition

Add a simple link from a source activity to a target activity to require the source to finish successfully before the target executes.
  1. Ensure that two activities are on the Process Editor canvas that you want to link.
  2. Select the source activity and then use
    Shift + select
    to select the target activity.
  3. Select the
    Link
    toolbar button or select
    Link Activities
    from the right mouse menu of one of the activities.
  4. Process Developer names the link
    L1
    . You can double-click the link to open the
    Transition Builder
    dialog.
  5. In the Properties view, you can rename the link, if desired.
Tip:
You can use the BPMN Edge tool in the Palette, if desired. To do so, select the tool and then select the source activity. Connect the link to the target, as shown on the left in the illustration. Select the
Select
tool to turn off the Edge tool.
Link between two activities